A licensed Florida PE walks through every Broward Building Safety Inspection deadline, from the certified-mail notice to the completion letter, and how it lines up with the state milestone inspection.

Short answer: Broward's Building Safety Inspection Program (BSIP) runs on two separate clocks. You have 180 days, counted from the date the Notice of Required Inspection is sent, to complete the structural and electrical inspection and submit the signed and sealed report, and the building official can extend that by up to 60 days. If the report calls for repairs, a second 180-day clock starts on the date of the report, unless the building official sets a different timeframe. For condominiums and cooperatives, the same BSIP inspection also satisfies the Florida milestone inspection, so you are not running a second inspection on a second schedule.
Below is each deadline in order, what can extend it, and what happens when one is missed.
| Step | Deadline | What has to happen |
|---|---|---|
| Notice of Required Inspection | Sent by certified mail, June through August | Your city notifies the owner or association that the building is due |
| Inspection and sealed report | 180 days from the date the notice is sent | Structural and electrical report on the BORA forms, signed and sealed, submitted to the building official |
| Report extension | Up to 60 more days, if the building official grants it | Request it before the deadline passes |
| Repairs, if required | 180 days from the date of the report, unless the building official sets a different timeframe | Permitted repairs completed |
| Completion | After repairs | Re-inspection by the original engineer and an amended report with a signed and sealed completion letter |
| Next inspection | Every 10 years from the year the first inspection was required | The cycle repeats |
The 180-day periods and the 60-day extension come from BORA Policy #05-05, the Broward County Board of Rules and Appeals policy that every Broward city follows. Each city administers the program, and the policy allows local agencies to set their own timelines and penalties, so read your notice carefully, note the date it was sent, and keep it with the certified mail receipt.
A building comes due when it reaches 25 years from its certificate of occupancy, and then every 10 years. Each June, BORA gives every Broward city a list of the buildings due that year. From June through August, the building official mails the Notice of Required Inspection by certified mail, return receipt requested, to the owner or association.
Three details catch owners out:
Single-family through four-family dwellings with three or fewer habitable stories, fee simple townhouses, minor structures under 3,500 square feet, and certain government and school buildings are exempt. For how these rules compare with Miami-Dade, see Broward vs. Miami-Dade: Key Differences. If your building is in Fort Lauderdale, our Fort Lauderdale BSIP page covers filing with the City.
Within 180 days of the date the notice is sent, the inspection has to be complete and the Florida-licensed engineer or architect has to issue the written report to the building official and to the owner or association. The report includes the completed BORA Structural and Electrical Safety Inspection report forms, a written narrative and color photos. It states that the building is structurally and electrically safe for continued occupancy, or it lists the repairs needed.
For a threshold building (more than three stories or taller than 50 feet), the structural portion must be prepared by a structural engineer licensed as a Special Inspector. The electrical report must be completed by a Florida-licensed professional specializing in electrical design.
Findings can also move the timeline up. Conditions that would endanger life or property if left unaddressed have to be reported to the owner, the association and the building official, and conditions that pose an immediate danger of failure or collapse have to be reported to the building official within 24 hours of discovery.
180 days is far more time than the inspection itself needs. The risk is the time lost before anyone calls an engineer, and whatever the inspection finds. Starting early leaves room for board approval, access to every unit and electrical room, and planning for repairs before the second clock starts. Our guide to what to do when a recertification notice arrives walks through the first steps.
Condominium and cooperative associations have one more task. The association must deliver a copy of the inspector-prepared summary of the report to every unit owner, post it in a conspicuous place on the property, and publish the full report and summary on the association's website if it is required to have one. Section 553.899, Florida Statutes gives the association 45 days after receiving the report to do this.
If the report calls for repairs, the owner has 180 days from the date of the report to complete them and correct the structural and electrical deficiencies, unless the building official specifies a different timeframe. Repairs follow the Florida Building Code and need permits. This second clock starts on the report date, not the notice date.
Repairs are done by a licensed contractor you hire, under permit. Mimik Solutions does not perform repairs. When the work is finished, the engineer who performed the original inspection re-inspects the areas noted in the report and issues an amended report with a signed and sealed letter stating that the repairs are complete and the building is acceptable for continued use. That letter goes to the building official to close the file. If your building needs that re-inspection, it is included in our original proposal. For budgeting, our Broward BSIP cost guide covers the typical range for the inspection and what a quote does not include.
BORA Policy #05-05 allows three kinds of extra time, each at the building official's discretion:
Extensions are requested, not automatic. The policy treats a missed report deadline without an extension request as a violation, so ask before the deadline, not after. Pompano Beach, for example, asks for the written extension request to come from a licensed engineer or architect qualified for the type of building (see the City of Pompano Beach BSIP page).
Each city enforces the program. Under BORA Policy #05-05:
Fines are set locally. The City of Hollywood, for example, says non-compliant buildings can be posted with a Notice of Violation and, if the owner does not respond, referred to the special magistrate, with fines of up to $1,000 per day for a first violation and up to $5,000 per day for a repeat violator (see the City of Hollywood BSIP page). Every one of these outcomes starts with a missed date, not with a bad inspection result.
After the Surfside collapse, Florida created the milestone inspection in Section 553.899, Florida Statutes for condominium and cooperative buildings three or more habitable stories tall. Broward's BSIP is broader: it covers most building types, not only condominiums, and it includes an electrical inspection. BORA Policy #05-05 states that the BSIP serves as compliance for both phase one and phase two of the milestone inspection, and buildings that completed an inspection under the earlier 40-year program are deemed compliant with Section 553.899.
| Broward BSIP | Florida milestone (s. 553.899) | |
|---|---|---|
| Applies to | Most buildings, with listed exemptions (including minor structures under 3,500 sq ft) | Condominium and cooperative buildings three or more habitable stories tall |
| Scope | Structural and electrical | Structural |
| First inspection | 25 years after the certificate of occupancy | By December 31 of the year the building turns 30 (or 25, if the local agency requires it) |
| Repeats | Every 10 years | Every 10 years |
| First deadline | 180 days from the date the notice is sent | Phase one within 180 days of the local enforcement agency's written notice |
| Further evaluation | Report identifies any items requiring further inspection | Phase two if substantial structural deterioration is found; progress report due within 180 days of the phase one report |
| Repairs | Completed within 180 days of the report, unless the building official sets another timeframe | Must begin within 365 days after the local agency receives the phase two report; local ordinance sets the exact timeframe |
| Unit owner summary | Delivered to every unit owner, posted on the property, and published online if required | Same, within 45 days of receiving the report |
In practice, the BSIP clock is the tighter of the two in Broward: the first inspection comes earlier and repairs have to be finished, not just started, within the repair window. A condominium that keeps to its BSIP deadlines is also covered for the milestone requirement. Miami-Dade works differently: qualifying condominiums follow the milestone process alongside the county's 40-year recertification, and the recertification report is due 90 days from the notice. Our milestone vs. recertification guide explains how those fit together, and our Miami-Dade recertification page covers the county process.
Here is how the dates work for a building whose Notice of Required Inspection is sent on July 15, 2026:
Use the dates on your own notice and report, and confirm the due date with your city's building department.
Send us your BSIP notice through the proposal form on our Broward BSIP page. You will get a fixed-fee proposal the same business day, and we will confirm your deadline from the notice. Once you approve, we schedule the inspection within 2 to 5 days and deliver the signed and sealed report within 48 hours of the inspection, which leaves most of the 180 days for planning any repairs. If a re-inspection is needed after repairs, it is included in our original proposal. Own several buildings in Broward or Miami-Dade? Mention all of them and we will quote them as one proposal. For general questions, use our contact page.
How long do I have to submit a Broward BSIP report?
180 days, counted from the date the Notice of Required Inspection is sent, to complete the inspection and submit the signed and sealed structural and electrical report. The building official may extend that by up to 60 days.
How long do I have to make repairs after a BSIP inspection?
A separate 180 days from the date of the report, unless the building official sets a different timeframe. If the work cannot reasonably be finished in 180 days, the building official can approve a longer timeframe specified by the engineer, as long as the repair permit stays active.
What happens if I miss a BSIP deadline?
The building official can send the case to a special magistrate or code enforcement board. Hollywood, for example, warns of fines of up to $1,000 per day for a first violation and up to $5,000 per day for a repeat violator. If required repairs are not made, the building can be deemed unsafe and unfit for occupancy.
Does a Broward BSIP inspection count as the Florida milestone inspection?
Yes. Under BORA Policy #05-05, the Building Safety Inspection Program serves as compliance for both phase one and phase two of the milestone inspection required by Section 553.899, Florida Statutes, so a condominium or cooperative does not need a separate milestone inspection.